Developed area: 2500 m²
Detail design, dismantling of old installations, installation the new ones, testing and commissioning assistance.
Installation: 10 km of cables, 110 lighting fixtures, MDB of 2000 A.
Modification of the route of busbar trunking system 1600 A.
Production, assembly and commissioning of other 8 energy distribution panels.
Installation of fire alarm system, burglary system, access control system, voice-data network.
Installation of HVAC system, 5 x AHUs, chillers, fan coil units, radiators.
Heating system, sanitary plumbing system, rainwater collection system, fire sprinkler system.