INDUSTRY:
Automotive
FOCUS:
Conveyor, Process and Application Technology
OBJECTIVE:
Electrical design in Eplan had to be finished in 4 weeks from PO and the cabinet was delivered on site 6 weeks later. The onsite installation lasted 4 weeks, followed by two weeks of commissioning assistance for IO check and startup with the client.
SOLUTION:
- Rittal VX25 enclosures
- Siemens safety PLC S7 1516F-3 PN/DP
- REVOLUTION PI RevPi Connect+ and VPN-Router eWon Cosy 131 for remote connectivity
- Siemens HMI TP 1900 Comfort
- Schneider protective devices
- Siemens G120 frequency drives
- Gefran thyristors
PROJECT DURATION:
4 months
THE PROJECT COMPRISED OF:
Process automation:
- 1 AHU with electric heating battery controlled with thyristors
- 1 Vapor evacuation equipment
- Lighting installations and monitoring installations of the filters for the paint booth
- 1 paint dryer with gas burner
Conveyors and application technology:
- 1 Preparation cabin (conveyors, hydraulic lifting platform, safety sensors)
- 1 Powder coating booth (conveyors, 5 paint robots, safety sensors)
- 1 Paint dryer (conveyors, safety sensors)
- Linear movement system for 2 robots
- 3 separation doors for the 3 areas (preparation, painting, drying)
- Robot rail system and paint distribution system
ELTREX PROVIDED THE FOLLOWING SERVICES:
- Electrical design in Eplan
- Production of the electrical panels in our workshop in Romania (main panel and secondary control stations)
- Electrical installation on site
- I/O check and start-up assistance