In this project, the client requested a complex Building Management System (BMS) for their 20,000 sqm refrigerated products logistics center in Romania.
In a recent project, we undertook the complete electrical engineering and automation for eight cold storage chambers, each with a 300 sqm volume, designed to operate between 15 and -20
Electrical design in Eplan had to be finished in 4 weeks from PO and the cabinet was delivered on site 6 weeks later.
The onsite installation lasted 4 weeks, followed by two weeks of commissioning assistance for IO check and startup with the client.